Bypass navigation and go to content
Collage of various archived materials

GTS Toolkit – What's Happening on Site

What we're doing What it involves
Bridge Sliding Bridge sliding is the process of literally sliding a pre-cast bridge into place. The bridge pieces are moved along slide paths into position by the power of computerized high-speed tandem hydraulic jacks. This process is a great advantage in a rail corridor because it only requires very short periods of track possession, which means the bridge sliding can take place without major disruptions to train schedules. Four bridge spans weighing a total of some 10,000 tonnes will be slid into their final positions at the West Toronto Diamond during the final phase of construction.
Bridge Span Installation The bridge span installation process begins off site, at a mill where pieces of the span are pre-built. The raw materials are tested for quality assurance, and then cut and welded together. Once the pieces are ready, they are assembled to ensure that none of the pieces are missing. The bridge is then unassembled and transported to the construction site, where a crane is used to lift the pieces into place. Main girders are installed first, followed by the panels. A cover plate is used to cover the abutment and handrails are installed. Once the bridge span is waterproofed and the ballast material has been installed, the tracks and ties can be laid.
Clearing and Grubbing Prior to construction, clearing and grubbing of the site area is done to ensure a clean and safe work area. Organic matter such as bush, trees and shrubbery are cut down and removed in accordance with the City of Toronto by-laws. Debris and garbage is also removed off site, making the work area free of any obstructions. The equipment used to conduct this work can include chain saws, wood chippers, loaders and dump trucks.
Excavation Essentially, excavation means digging or removing soil; what varies is the function of the dig. At a construction site, excavation can take place at nearly all phases of a project for different reasons. For example, we excavate when we dig up the dirt around buried utilities such as wires, cables and water mains that need to be relocated before major construction can begin. We also excavate as an entire phase of construction where a tunnel is being dug in order to lower the rail corridor below grade. However, before any excavators can get to work, temporary shoring or retaining walls must already be in place to keep the soil from backfilling into the hole as it is being removed.
Forming of Walls Forming of walls occurs when concrete walls are poured in place. Wood or aluminium forms are set into place at the locations where the walls will be going and concrete is poured in between. The concrete is allowed to cure or harden and then the forms are removed, leaving behind the concrete walls. At the deepest point of the Weston Tunnel, the tunnel walls will be 12 metre deep.
Forming of Urban Surface An urban surface will be created by the construction of the lid for the Weston Tunnel. This will be built by installing scaffolding below the surface and putting forms into place in 20 metre sections. Concrete will then be poured into the forms and left to cure and then the scaffolding will be removed. The concrete will be approximately 1 metre thick and will be strong enough to support a significant amount of weight that would allow for earth and grass to be put in place, and allow the surface to be used for other purposes.
Installation of Struts Struts provide outward-facing support for retaining walls that are required for the lowered rail corridor. The struts are lifted into place using a crane and then secured into the retain wall using bolts. For the Strachan Avenue Overpass, struts will span across the corridor from the section between Stanley Terrace and Shaw Street to support the north and south retaining walls.
Jack and Bore This is a method that installs a pipe through the earth while simultaneously removing earth spoil from the casing through a rotating auger inside the casing. Also referred to as auger boring or horizontal boring, it ensures little or no disruption to surrounding businesses, residents or the environment.
Pile Installation Piles come in different shapes and sizes and are installed in different ways, depending on what is appropriate for local ground conditions and the type of structure they are being used to build. At the West Toronto Diamond, interlocking steel pipe-piles and sheet-piles are driven into ground using vibration, push and impact methods to create the retaining wall for the lowered corridor and to hold up the two bridges. At other worksites along the corridor, some piles will be formed by pouring concrete into a hole, which is called auger cast in place piling. Regardless of the shape and size, all piles have a similar function: they form a foundation and distribute the weight load of the bridge, tunnel or structure being built.
Pile Validation Pile validation is the process of removing soil from within pipe piles and filling them with concrete and other sealing materials to create a water tight foundation wall. Large crane mounted augers and drum cleaners remove the dirt and sweep the sides of the piles and then a trailer mounted concrete pump fills them with concrete and other sealing materials, such as types of grout to fill in tight spaces. At the West Toronto Diamond, pile validation defines the second last phase of construction – it follows pile installation and must be complete before excavation can occur in the same area.
Road Cuts A road cut is the process of cutting into the road, and is needed to expose any water or sewer pipe lines that exist beneath a paved road. Prior to actually cutting the road, a permit is required from the proper authorities, such as the City of Toronto. This work is done in conjunction with utility relocation work for water and sewer pipe lines.
Shoring Shoring is used in construction to provide support against the weight of soil to allow excavation to take place safely and prevent cave-ins. This will be used for underground utility work, such as at Denison Road and the Lawrence Avenue Bridge. It will also be used in the construction of the Weston Tunnel where steel columns will be augured into the ground with vertical wooden beams used to create the shoring wall.
Signal Installation Signalling systems are used to move trains efficiently and communicate the location of trains on the tracks. The Georgetown South Corridor is undergoing a full signal upgrade to accommodate the service improvements that will be taking place. The upgrades to the signalling system will allow the trains to run at shorter intervals in order to accommodate the increase in service in GO Trains and the new Air Rail Link service. Along the corridor, signals are in place approximately 1 kilometre apart at key intervals such as crossovers and level crossings. Signals include a mix of hard wire and wireless transmission systems providing redundancies in case of a failure.
Signal Maintenance Regular maintenance of signals ensures that the system is in full working order. Manual checks of the tracks and signals occur monthly to confirm that the tracks and signals are clear of debris and operating as expected. A train simulator device is used to determine that the system is operating as expected. The removal of level crossings taking place in the Georgetown South Project, such as those at Strachan Avenue and Carlingview Drive, will dramatically increase the safety and signal reliability.
Tie-back Installation Tie-backs are installed by the contractor to hold up walls against pressure pushing them inward. They can be made from wire or rods that extend into rock or earth. Tie-backs will be used to support several shoring walls throughout the GTS Project, such as the Weston Tunnel. The tie-backs used for the Weston Tunnel will be approximately 13 metres long and will extend down into the ground to support the temporary shoring wall. Each tie-back will consist of six to seven cables, each a half inch in diameter. When the tie-back support is no longer needed, they will be cut off and left in place.
Track Shifts/Track Detours A track shift is when train tracks are moved from their original location to another. Essentially, the old sets of tracks are removed and a new set of tracks are installed to allow trains to travel on. Often, this is done to allow construction workers to work in the area of the original tracks. Depending on the type of train corridor, this work can be done anytime a train is not passing. If it is a live corridor, this work is usually done at night, or at other times when trains are not travelling through the corridor. To shift a track, the material for the new track is brought on site, ballast material is put down, tracks are laid, and a tamper is used to make sure the ground is level and the soil is packed. A track stabilizer puts the finishing touches and pinches everything into place using vibrations. Track shifts/detours are done prior to major excavation. Once the excavation is complete the tracks are put back into their original location. For example, at the Weston Tunnel, tracks will be shifted to allow excavation on the tunnel itself to be completed. After the tunnel is created, the tracks will be placed back in the same location.
Utility Relocation Prior to construction along the GO Transit train corridor, any fibre optic cables and utilities need to be removed from under the rail corridor. Often, electric, telephone and cable companies have their lines buried beneath the train tracks or on GO Transit property. Each respective utility company is responsible for the relocation of their own lines from the existing location, to one that is out of the way of construction. Coordination of this work between each utility company is done in cooperation with the contract administrator. Toronto Hydro and gas companies are also part of the utility relocation phase. For example, if work is being done near or on a road, there are water, sewer and gas mains which run into each residential/commercial property from the main municipal connection underneath. Once again, work is conducted by each respective company to remove pipes which are in the way of the build. One example of this is at the Denison Road Underpass, where the contract administrator coordinates work with Toronto Hydro and Enbridge. To conduct this work, the road is cut and soil is excavated to expose pipe lines using a hydrovac and a backhoe.
Noise wall Committees GTS Toolkit

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
NEW 44 King Street
Toronto, ON M9N 1L1
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only