Bypass navigation and go to content
Galt Sub looking West

West Corridor Bridges

The West Corridor Bridges work package involves widening for railway bridges in the western portion of the Georgetown South corridor: Kipling Avenue, Martin Grove Road, Highway 27 and Highway 427.

Updates

  • April 29 – In April, we completed installation of girders (bridge decks) at the bridges at Highway 27, Martin Grove Road and Kipling Avenue. The girder installation work was completed on the weekends to facilitate lane restrictions/road closures as required. At Highway 27, we are now backfilling the wing wall, and forming and pouring the bridge, completing the installation of the trainman’s walkway, the expansion joints and completing waterproofing. A trainman’s walkway is a steel grate walkway with railing that allows the train crew to safely step off and walk around the train if needed. We are also preparing to install a trainman’s walkway and place ballast on the bridge at Martin Grove Road. At Kipling Avenue, we are relocating utilities within the southbound sidewalk, to be able to reopen the sidewalk to the public. The work at the West Corridor Bridges is expected to be completed this summer.

Kipling Avenue

Project Schedule

  • Construction start: Fall 2012
  • Construction complete: Summer 2013

What we are doing

  • We are adding new spans to the existing bridge to accommodate more tracks

How this will affect you

  • There will be lane restrictions for the duration of the work and occasional weekend road closures during construction.
  • From December 17, 2012 to Spring 2013, the east sidewalk which connects Etobicoke North GO Station and the north parking lot will be unavailable. A temporary walkway will be provided to maintain access.

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Dagmar Construction

Community Updates

 

Martin Grove Road

Project Schedule

  • Construction start: Fall 2012
  • Construction complete: Summer 2013

What we are doing

  • We are adding new spans to the existing bridge to accommodate more tracks

How this will affect you

  • There will be lane restrictions for the duration of the work and occasional weekend road closures during construction

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Dagmar Construction

Community Updates

 

Highway 27

Project Schedule

  • Construction start: Fall 2012
  • Construction complete: Summer 2013

What we are doing

  • Add new spans to the existing bridge to accommodate more tracks

How this will affect you

  • There will be lane restrictions for the duration of the work and occasional weekend road closures during construction

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Dagmar Construction

Community Updates

 

Highway 427

Project Schedule

  • Design Completion: Complete
  • Construction started: Fall 2011
  • Construction completed: June 2012

What we are doing

  • We have built a retaining wall under the bridge at Highway 427 to accommodate two additional tracks
  • This work was phase 1 of the West Corridor Bridge package

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Aecon

Community Updates

For updates from 2010 or 2011, please see our Communication Materials page.

Noise wall Committees GTS Toolkit

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
NEW 44 King Street
Toronto, ON M9N 1L1
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only